Yamana receives expansion permit for Jacobina

7th December 2021 By: Mariaan Webb - Creamer Media Senior Deputy Editor Online

Yamana receives expansion permit for Jacobina

Canadian gold miner Yamana Gold has received the permit at its Jacobina mine, in Brazil, to expand throughput to 10 000 t/d, marking not only a significant milestone in the Phase 2 ramp-up to 230 000 oz/y, but also facilitating the future Phase 3 expansion to bring production up to 270 000 oz/y.

The company reported that it would immediately begin to ramp up throughput to the Phase 2 rate of 8 500 t/d, from the previously permitted rate of 7 500 t/d. The Phase 2 objective of 8 500 t/d would be achieved by the second quarter of 2022 – about a year earlier than originally planned, Yamana reported on Monday.

The miner also stated that it had simplified its approach for the Phase 2 expansion, which reduced capital expenditure, increased energy efficiency and derisked the project. The capital costs for the Phase 2 expansion were estimated at $20-million, of which $15-million would be spent next year.

Engineering for the potential Phase 3 expansion was advancing in parallel with Phase 2, with a feasibility study for Phase 3 to be completed in 2023.

Meanwhile, Yamana reported that it expected to exceed its 270 000 gold-equivalent ounce (GEO) guidance for the fourth quarter and that its yearly production guidance of one-million GEOs would also be exceeded.

Fourth-quarter costs were tracking to be the lowest of the year. All-in sustaining costs (AISC) were forecast to be $980/GEO or lower, which the company noted was 7% below the AISC reported for the prior three quarters.