North Bullfrog gold/silver project, US

27th November 2020 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

North Bullfrog gold/silver project, US

Name of the Project
North Bullfrog gold/silver project.

Location
North-west Nevada, in the US.

Project Owner/s
Corvus Gold.

Project Description
The results of a preliminary economic assessment have outlined a potentially big standalone mining project, with attractive preliminary production and financial performance statistics.

The project has measured and indicated resources of 2.1-million ounces of gold and 10.3-million ounces of silver. Inferred mineral resources are estimated 410 000 oz of gold and 1.29-million ounces of silver. The North Bullfrog project is modelled as a large openpit, run-of-mine, heap-leach operation, with a grinding circuit for gravity gold recovery of the high-grade YellowJacket vein and stockwork deposit.

The mining plan uses standard mining practices and has a production scale that is being used by many operating openpit mines in Nevada.

The project has a mine life of 14 years, with life-of-mine production estimated at 1.47-million ounces of gold and 3.2-million ounces of silver.

The operation will produce 147 000 oz/y of gold and 400 000 oz/y of silver in the first seven years.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Using a gold price of $1 500/oz of gold, the project has an after-tax net present value, at a 5% discount rate, of $452-million and an internal rate of return of 47%, with a payback of 2.1 years.

Capital Expenditure
Initial capital is estimated at $167-million.

Planned Start/End Date
Not stated.

Latest Developments
None stated.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Corvus Gold, tel + 1 604638 3246 or email info@corvusgold.com.