Nevada's Cove project has 102 000 oz/y potential, says Premier

19th January 2021 By: Mariaan Webb - Creamer Media Senior Deputy Editor Online

Nevada's Cove project has 102 000 oz/y potential, says Premier

The Cove project, at the McCoy-Cove property in Nevada, US, will produce an average of 102 000 oz/y over its eight-year mine life, Ontario-based Premier Gold Mines said on Monday.

The project will be one of the cornerstone assets of the soon-to-be-spun-out i-80 Gold, which will focus on gold exploration and development in Nevada.

Announcing updated preliminary economic assessment (PEA) results, Premier said that Cove had indicated resources of 1.11-million tons at 0.316 oz/t of gold and 0.855 oz/t of silver for 351 000 oz of gold and 943 000 oz of silver.

Over its eight-year life-of-mine (LoM), Cove would produce 743 000 oz.

The project’s LoM capital cost is estimated at $107.2-million, after predevelopment costs of $23.9-million. Mine construction capital has been pegged at $81.9-million tonnes.

The PEA yielded an after-tax net present value of $178-million and an internal rate of return of 36%, based on a gold price of $1 400/oz.

“Our go-forward plans for the project include an exploration ramp to allow an aggressive underground drill programme to upgrade and expand mineral resources in advance of a future feasibility study and also provide a platform to increase recoverable gold resources and delineate the deposit still open down-plunge,” said president and CEO Ewan Downie.

The McCoy-Cove property is located immediately south of Nevada Gold Mines’ Phoenix mine.