Mogale Gold tailings storage facilities, South Africa – update

28th July 2023 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Mogale Gold tailings storage facilities, South Africa – update

Photo by: Pan African Resource

Name of the Project
Mogale Gold tailings storage facilities (TSFs).

Location
Near Krugersdorp, to the west of Johannesburg, in Gauteng, South Africa.

Project Owner/s
Pan African Resources.

Project Description
The Mogale Gold TSFs comprise various individual dams containing a probable mineral reserve of 123.6-million tonnes of remineable material at a head grade of 0.29 g/t for an estimated content of 1.14-million ounces of gold.

The Mogale Gold project has the potential to increase Pan African’s gold production profile over the coming years.

Remining the Mogale Gold TSFs is expected to add about 50 000 oz/y of production over its 13-year life-of-mine (LoM). The project entails low unit-cost hydromining, with low project execution risk, at 800 000 t a month using a carbon-in-leach plant, similar to Pan African’s Elikhulu operation currently processing 1.2-million tonnes a month, with up to 900 000 t a month achievable without negatively affecting performance.

The addition of Mintails’ Soweto Cluster resource has the potential to extend the LoM from 13 years to 21 years and further increase yearly gold production.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 9.5% real discount rate, of R1.01-billion and a real ungeared internal rate of return of 20.1%. Construction capital payback is estimated within 3.5 years after commissioning.

Capital Expenditure
Construction capital expenditure is estimated at R2.46-billion.

Planned Start/End Date
Construction started in July 2023.  The commissioning the project is expected between July and December 2024. 

This project is expected to be at steady-state production during the first half of the 2025 calendar year.

Latest Developments
The official sod-turning ceremony for the construction of the Mogale tailings retreatment project was held on July 25.

The project's engineering, procurement, construction management (EPCM) contractor is SGS Bateman.

Key Contracts, Suppliers and Consultants
DRA Projects (definitive feasibility study) and SGS Bateman (EPCM).

Contact Details for Project Information
Pan African Resources, tel + 27 11 243 2900 or email info@paf.co.za.