KSM – additional block cave, Canada

2nd December 2022 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

KSM – additional block cave, Canada

Name of the Project
KSM – additional block cave.

Location
Northern British Columbia, Canada.

Project Owner/s
Seabridge Gold.

Project Description
A preliminary economic assessment (PEA) has demonstrated that KSM has the potential to be a multigenerational, long-life copper-rich mining project with the flexibility to vary metal output.

The 2022 PEA has been undertaken to evaluate the potential future expansion of the KSM mine into the copper-rich Iron Cap and Kerr deposits after the 2022 preliminary feasibility study mine plan has been completed.

The 2022 PEA envisages an underground mining operation, starting with the development of an Iron Cap block cave mine and supplemented with a small openpit at Kerr.

Development of the Kerr block cave mine will start when the Iron Cap development tapers off. The Kerr block cave mill feed will start six years after the start of the Iron Cap mill feed.

Mill feed delivery to the process plant will be ramped up to 170 000 t/d by Year 12.

Over the 39-year life-of-mine (LoM), mill feed will be delivered to a flotation concentration mill circuit. The flotation plant will produce a gold/copper/silver concentrate and separate molybdenum concentrate for transport by truck to a nearby seaport at Stewart, in British Columbia.

The project will produce 14.3-billion pounds of copper, 14.3-billion ounces of gold, 68.2-million ounces of silver and 13.8-million pounds of molybdenum from 1.7-billion tonnes of mill feed over the LoM.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
In the base case, the project has a pretax net present value, at a 5% discount rate, of $9.7-billion and an internal rate of return of 24%, with a payback of 4.7 years.

Capital Expenditure
The initial capital cost for the 2022 PEA is estimated at $1.5-billion.

Planned Start/End Date
The development of the Iron Cap block cave mine will take four years and that of the Kerr block cave five years.

Latest Developments
None stated.

Key Contracts and Suppliers
Tetra Tech (surface infrastructure, capital estimate, financial analysis, metallurgical testing review, permanent water treatment, mineral process design and operating cost estimation for process, general and administrative expense and site services, and overall report preparation); Wood (mineral resources); WSP Golder (block cave mining); Moose Mountain Technical Services (openpit mining, MTT and rail mill feed conveyance design, tunnel capital costs); WN Brazier Associates Inc (electrical power supply, energy recovery plants); Environmental Resources management (environment and permitting); and Klohn Crippen Berger (design of surface water diversions, diversion tunnels, tailings management facility, water treatment
dam and rock storage facility and tunnel geotechnical).

Contact Details for Project Information
Seabridge Gold, tel +1 416 367 9292 or email info@seabridgegold.com.