Kasiya rutile project, Malawi

4th March 2022 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Kasiya rutile project, Malawi

Name of the Project
Kasiya rutile project.

Location
Malawi.

Project Owner/s
Sovereign Metals.

Project Description
Kasiya is the biggest undeveloped rutile deposit in the world. Total mineral resources are estimated at 605-million tonnes grading 0.98% rutile and 1.24% total graphitic carbon.

The initial scoping study on the project has developed the concept for a multidecade mine providing a consistent supply of a highly sought-after rutile and graphite while contributing to Malawi’s economy. The proposed large-scale operation will process soft, friable mineralisation mined from surface and will primarily use conventional hydromining to produce a slurry that will be pumped to a wet concentration plant where the material will be sized.

A heavy mineral concentrate will be produced by processing the sand fraction through a series of gravity spirals, after which it will be transferred to the dry mineral separation plant where premium quality rutile will be produced using electrostatic and magnetic separation. Graphite-rich concentrate will be collected from the gravity spirals and processed in a separate graphite flotation plant, producing a coarse-flake graphite product.

The mine will have a throughput of 12-million tonnes a year over a 25-year mine life, producing 122 000 t/y of rutile and 80 000 t/y of graphite.

The rutile and graphite products will be trucked a short distance using existing bitumen roads to the Kanengo rail terminal, from where they will be railed through the Nacala Logistics Corridor to the deep-water port of Nacala on the eastern seaboard of Mozambique.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% discount rate, of $861-million and an internal rate of return of 36%, with a payback of 2.5 years.

Capital Expenditure
$332-million.

Planned Start/End Date
Not stated.

Latest Developments
The current mining inventory covers 49 km2, or 38%, of the total drill-defined area of high-grade rutile mineralisation of 129 km2. Sovereign Metals expects to materially increase the overall mineral resource estimate tonnage in early 2022, which will allow for the study options to be reviewed in terms of potential for scale-ups or mine-life extensions beyond the current 25 years.

Key Contracts, Suppliers and Consultants
DRA (lead study manager); Jem-Met (project management); Placer Consulting (mineral resource estimate); Oreology Mine Consulting (mine scheduling and pit optimisation); Fraser Alexander (mining methods and tailings management); Epoch Resources (tailing disposal); AML (metallurgy – rutile); SGS (metallurgy – graphite); Dhamana Consulting (environment and social studies); JCM Power (power); TZMI (marketing – rutile); Fastmarkets (marketing – graphite); Morgan Sterling Consultants (logistics) and Minviro (life-cycle assessments).

Contact Details for Project Information
Sovereign Metals, tel +61 8 9322 6322 or email info@sovereignmetals.com.au.