Kamoa-Kakula Phase 1 concentrator exceeds steady-state design throughput

15th October 2021 By: Creamer Media Reporter

The 3.8-million-tonne-a-year Phase 1 concentrator at Ivanhoe Mines’ Kamoa-Kakula mine, in the Democratic Republic of Congo, milled 319 795 t of ore in September, exceeding the monthly design run rate of 316 667 t.

A total of 16 010t of copper in concentrate were produced (filtered product) and a total of 16 503 t floated in the reporting month ended September 20 – Kamoa Copper’s fourth full month of production – establishing a new monthly record and nearing the Phase 1 target output of 16 666 t a month, or 200 000 t/y.

The difference between filtered and floated copper is about 500 t in inventory in the concentrate thickener and the filter feed tank, Ivanhoe notes.

The average floated concentrate copper grade in September improved to 55.7%, up from about 48% in August.

A total of 46 764 t of copper in concentrate has been produced year-to-date for delivery to either the Lualaba copper smelter, near Kolwezi, or to international markets.

Copper flotation recoveries improved to an average of 85.1% during September, up from an average of 83% during August. The Phase 1, steady-state-design copper recovery is about 86%, depending on ore feed grade.

A daily record copper recovery of 88.3% was achieved on September 12 and a daily floated copper production of 721 t was achieved on September 15.

Subsequent to the reporting period, a daily milling record of 12 596 t and a daily crushing record of 14 778 t were achieved on September 27.

“The Kamoa-Kakula team has worked tirelessly to bring the Phase 1 concentrator to steady-state performance. We are very pleased with the September results, where we exceeded steady-state design parameters for ore throughput and were close to achieving steady-state design copper recovery and monthly copper production,” comments Kamoa Copper CEO Mark Farren.

He adds that a number of further adjustments are being made to the Phase 1 processing circuit to enable the concentrator to achieve better results in the next quarter.

Kamoa-Kakula is fast-tracking the commissioning of an additional concentrate filter, which has been installed alongside the Phase 1 filter, to be able to take advantage of copper feed grades and milling rates in excess of design parameters. The additional concentrate filter is expected to be fully operational this month, enabling the Phase 1 concentrator to produce more copper than its design capacity of about 200 000 t/y.

“These adjustments, which also will be incorporated into the Phase 2 processing circuit, should position us to achieve 2021 copper production in the upper end of our previous guidance of 80 000 t to 95 000 t. This gives us the confidence to raise the range to 85 000 t to 95 000 t,” says Farren.

Meanwhile, construction of the 3.8-million-tonne-a-year Phase 2 concentrator plant is also progressing well, with the overall project more than 50% complete. Engineering and procurement activities are effectively complete, with fabrication at 86% completion.

Civil construction works are effectively complete, with the focus now on the erection of structural steel and the installation of platework and equipment. A 400 t crane has arrived on site and has been used to lift the tailings thickener rake into position.