Name and Location
Iron-ore beneficiation plant, Iran.
Client
Khorasan Steel Complex Co.
Project Description
The project involves the construction of an iron-ore beneficiation plant.
The plant will deliver 2.5-million tonnes of pellet feed-grade iron-ore concentrate a year.
Net Present Value/Internal Rate of Return
Not stated.
Value
Not stated.
Duration
The plant is expected to be commissioned in 2017.
Latest Developments
Iran International Engineering Company has awarded Outotec a contract for the delivery of process technology to Khorasan’s new iron-ore beneficiation plant.
The scope of delivery includes a complete beneficiation plant and an entire value chain – from raw materials testing and process development to concentration and dewatering.
Outotec will also be responsible for basic engineering and the supply of key process equipment, as well as advisory services for detail engineering, construction and commissioning.
Key Contracts and Suppliers
Outotec (process technology).
On Budget and on Time?
Not stated.
Contact Details for Project Information
Khorasan Steel Complex Co, tel +98 511 8451102 or fax +98 511 8451101.
Outotec director of corporate communications Eila Paatela, tel +358 20 529 2004, fax +358 400 817 198 or email firstname.lastname@outotec.com.