Browns Range heavy earths pilot plant development project, Australia

4th August 2017 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Browns Range heavy earths pilot plant development project, Australia

Name of the Project
Browns Range heavy earths pilot plant development project.

Location
Western Australia.

Client
Northern Minerals.

Project Description
The Browns Range pilot plant will be used to assess the economic feasibility of a full-scale project and forms part of a broader ongoing feasibility study underpinning the Browns Range rare earths project. The Browns Range project will focus on the production of dysprosium.

The pilot plant is expected to operate for three years initially, with a throughput of 60 000 t/y. This is about 10% of the size of the full-scale development to assess, refine and confirm the optimal flowsheet.

The ore will be processed from two separate openpits – Wolverine and Gambit West – of varying depths and mineral concentrations to determine the optimal flowsheet for the proposed full-scale development.

Owing to the small volumes involved in the pilot plant project (180 000 t over three years), Northern Minerals has decided to mine all this material in one campaign in 2017, with ore stockpiled on the run-of-mine pad.

During the three-year pilot project, the plant is expected to produce 1 719 000 kg of total rare-earth oxide in a mixed rare-earth carbonate containing 148 200 kg of dysprosium.

The pilot plant is the precursor to the development of a full-scale A$329-million project, which has been modelled over an initial life of 11 years, and which will produce 585 00 t of high-value heavy rare earths.

Jobs to Be Created
The project is expected to create 50 construction jobs and 45 ongoing operational positions.

Net Present Value/Internal Rate of Return
Not stated.

Value
The project has a capital cost of A$56-million.

Duration
The project will take 11 months to build, with mixed rare-earth carbonate production expected in mid-2018.

Latest Developments
Western Australian Premier Mark McGowan has broken ground at the Browns Range rare earths project, marking the start of work at the pilot plant operation.

Meanwhile, operations are ramping up at the Browns Hill project, with mining having started in June, and with contractors arriving on site to start preparation work at the processing plant modules under construction in China.

Key Contracts and Suppliers
Sinosteel MECC (engineering, procurement and construction contract).

On Budget and on Time?
Not stated.