Bafokeng Rasimone Platinum Mine North Shaft Merensky Phase III project, South Africa

27th October 2017 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Bafokeng Rasimone Platinum Mine North Shaft Merensky Phase III project, South Africa

Name of the Project
Bafokeng Rasimone Platinum Mine (BRPM) North Shaft Merensky Phase III project.

Location
North West, South Africa.

Client
BRPM Joint Venture (JV), comprising Royal Bafokeng Platinum (RBPlat) and Anglo American Platinum (Amplats).

Project Description
The BRPM Phase III project is providing further replacement for Merensky production at the North shaft complex through the extension of the existing decline system from Level 10 to Level 15 at the mine boundary.

At steady state, Phase III will maintain the production level of the North shaft at about 100 000 t/m.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
Not stated.

Value
R1.409-billion.

Duration
The project started in November 2010 and is scheduled for completion in 2018.

Latest Developments
RBPlat has reported that expenditure at the BRPM Phase III replacement project for the quarter ended September 30, was R9.7-million, bringing the total project expenditure to date to R1.05-billion.

Project progress and expenditure remain aligned with the current construction schedule required to complete the scope of work pertaining to the installation of services, conveyor belts and associated bulkheads on 14 and 15 levels.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
The project remains below budget and on schedule.

Contact Details for Project Information
RBPlat executive for corporate affairs Mpueleng Pooe, tel +27 10 590 4515 or email mpueleng@bafokengplatinum.co.za.
Amplats corporate communications, Mpumi Sithole, tel +27 11 373 6246, fax +27 11 373 5846 or email Mpumi.sithole@angloamerican.com.