Avoid that sinking feeling on underground development projects by using target cost contracts

2nd February 2023

Avoid that sinking feeling on underground development projects by using target cost contracts

Natalie Reyneke of MDA Attorneys

Shaft sinking and underground development projects for new and existing mines are high risk endeavours given the lack of predictability in underground geological, hydrogeological and geotechnical groundmass charac-teristics. These risks are compounded by factors such as the location of the mine and the fact that there are a limited number of contractors capable of successfully executing these projects.  These unique factors mean that the typical contracting strategies employed for most construction projects (i.e., lump sum or re-measurable contracts) are unsuitable for these projects.

Despite FIDIC releasing its Conditions of Contract for Underground Works in 2019 (the Emerald Book), there has been limited uptake of this contract in mining projects as, in the authors’ view, most employers are uncomfortable taking on all of the risk associated with the nature of underground works.  

MDA Attorneys has been involved in the drafting and negotiation of many shaft sinking and underground development contracts and has been instrumental in advancing the use of target cost contracts to effectively manage the unique risks presented by these projects.

The reality with shaft sinking and under-ground development projects is that if certain risks materialise, the costs associated with dealing with these risks could be extensive, resulting in major losses to a contractor under the typical contracting strategies.  If the employer wants to avoid a situation where the contractor either overprices the contract or loses significant sums of money (and the additional risks such scenario presents), then the adopted contracting strategy has to reflect an equitable balance of these unique risks.

Target cost contracts allow for the parties to agree a target cost to execute the project, together with mark-up for profit. The parties also agree which risks, if they materialise, will adjust the target cost. As the work is executed the contractor is paid its cost – and as risks materialise, the target cost is adjusted. Ultimately, at the end of the project, the cost paid to the contractor is reconciled against the adjusted target cost and any cost savings or over-runs are shared between the parties.

Provided it is structured correctly, this contracting strategy allows for the contractor to accurately price for the work knowing that should certain risks materialise, these will be dealt with on an equitable basis, and it is unlikely that company-threatening losses will be incurred. In return, the employer is provided with insight into how the contractor has structured its costs and can participate in evaluating the proposed methods of working to interrogate possible cost savings. A key feature of this contracting strategy is that it provides flexibility to the parties as to how they approach and deal with each specific risk. The employer can also assume certain risks which are fully within its control (for example access to the workface for the sinking of a sub-vertical shaft in an existing mine). The purpose of this contracting strategy is to align the objectives of both parties in reducing the cost and time of executing the project.

Examples of this contracting strategy’s ability to address the unique risks in underground projects include:

In conclusion, shaft sinking and under-ground development projects are high risk projects that require a contracting strategy that motivates the parties to work together to reduce costs and time. In our experience, a properly priced and negotiated target cost contract, with suitable share ratios achieves this goal.