Woodside flags cost increase at Scarborough

4th August 2021

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

KALGOORLIE (miningweekly.com) – Oil and gas major Woodside has flagged a 5% increase in the capital cost estimate for its Scarborough development, ahead of a final investment decision (FID) later this year.

The company on Wednesday said that the project would cost an estimated $12-billion to develop, comprising a $5.7-billion investment for the offshore component and a $6.3-billion investment for the onshore component.

The price increase, resulting from refreshed pricing from major contractors, underpins the updated cost estimate, and reflects Woodside’s work with them since 2020 to maximise the value of the project by optimising design and execution planning, and increasing offshore processing capacity.

The cost increase incorporates an approximately 3% cost increase in the onshore component, including modifications to Pluto Train 1 to enable processing of Scarborough gas, and an approximately 8% increase in the offshore component, including an increase in offshore production capacity from 6.5-million tonnes a year to 8-million tonnes a year of liquefied natual gas (LNG) and an additional well.

Woodside acting CEO Meg O’Neill reaffirmed that the Scarborough development was a transformational project that would deliver enduring shareholder value.

“Significant progress has been made towards our targeted FID on Scarborough and Pluto Train 2 this year.

“The cost update includes value-accretive scope changes to deliver an approximately 20% increase in offshore processing capacity and to modify Pluto Train 1 to allow increased Scarborough gas processing. It also reflects the work undertaken with our contractors to optimise the execution schedule and manage costs in preparation for FID.

“Woodside’s contracting strategy for Scarborough reduces cost risk, with approximately 90% of total project contractor spend structured as lump-sum and fixed rate agreements.

“We have commenced the formal processes for selling down our interest in Pluto Train 2 and Scarborough as we target the investment decision later this year and these processes are supported by the updated cost estimate,” she said.

Woodside noted that the expected internal rate of return of the integrated Scarborough and Pluto Train 2 development was greater than 12%, and the project had a globally competitive cost of supply of approximately $6.8 per metric million British thermal units to north Asia and was targeted to deliver the first cargo in 2026 into a market with anticipated robust demand for LNG.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION