Updated PEA forecasts 44% more gold from Marathon’s Valentine Lake

31st October 2018

By: Creamer Media Reporter

     

Font size: - +

Toronto-headquartered Marathon Gold has unveiled an updated preliminary economic assessment (PEA) for the Valentine Lake Gold Camp, in Newfoundland, announcing a 44% increase in the recovered gold and improved economics.

Compared with the May 2018 PEA, Valentine Lake will deliver 827 000 oz more recovered gold at 2.72-million ounces, producing an average of 225 100 oz/y over a 12-year mine life. The previous study estimated total recovered gold of 1.89-million ounces, for 188 500 oz/y over a ten-year life.

The updated study calculated an after-tax net present value (NPV) of $493-million using a 5% discount rate. The financial model shows an after- tax internal rate of return (IRR) of 30% and a capital payback period of 2.5 years. The May study estimated an NPV of $597-million and an IRR of 34%.

Marathon president and CEO Phillip Walford explained that the updated study benefited from 20 000 m of additional drilling since February, 9 000 metallic screen assays on historical drill core since the last PEA resource, and an internal review of the project.

“For example, initial and sustaining capital costs have been cut by leasing the mining fleet instead of purchasing it. The very positive improvements in production and mine life are attributable to this year’s successful drilling programme to extend the openpit resources at the Marathon deposit, a major gold deposit that continues to grow thereby driving expansion of the project. Early near-surface higher grade resources with a low strip ratio at the Marathon deposit enable high gold production in the early years of the operation and a fast payback of capital,” he said.

Walford added that the PEA had capitalised on several opportunities identified in the May PEA, and there was still room for further improvements to the mine plan and economics for the 2019 prefeasibility study.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION