Royal Bafokeng Platinum engaged in tailings, concentrator, conveyor projects

10th March 2021

By: Martin Creamer

Creamer Media Editor

     

Font size: - +

JOHANNESBURG (miningweekly.com) – Platinum group metals mining company Royal Bafokeng Platinum (RBPlat) has tailings, concentrator and overland conveyor projects under way, which are aimed at achieving organic growth as well as long-term sustainability.

RBPlat executive head of operations Neil Carr reported at the company's presentation of record financial results that the company was building a tailings storage facility (TSF) at the company’s BRPM mine, which it estimates will cost R458-million on completion in the first quarter of 2022. (Also watch attached Creamer Media video.)

For tailings deposition at the Maseve TSF, key construction works required have been completed at a cost of R112-million, an expansion that extends the life of the facility by an additional 13 years.

RBPlat is also active on the upgrade of the Maseve concentrator to 180 000 t a month at an estimated R496-million cost on completion in the third quarter of this year.

Project studies under way include the evaluation of the second phase of the 3 km overland conveyer from BRPM to Maseve, the identification of incremental improvements in concentrator capacity for the Maseve and BRPM plants and a life-of-mine optimisation study at the Styldrift mine, which is entering the steady state phase.

In response to Bank of America mining analyst Patrick Mann on the overland conveyor, Carr explained that currently mined ore is trucked between BRPM and Maseve.

“The logistics do get quite complex when we’re transporting up to 200 000 t a month of ore and the conveyor will certainly help with the logistics of that. It’s about a three kilometre route between the two concentrators.

“We're going into an environmental approvals process for that, which can often be quite long and procedural, but there’s also a cost benefit to the overland conveyor. You can imagine the rand-per-tonne trucking cost compared with a conveyor.

“We’ll continue pursuing that to understand the capital spend required for the overland conveyor and undertake the environmental process before we can actually construct,” Carr said.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION