Paragon advances Lesotho kimberlite work programmes

14th January 2013

By: Natalie Greve

Creamer Media Contributing Editor Online

  

Font size: - +

JOHANNESBURG (miningweekly.com) – Aim-listed Paragon Diamonds on Monday announced the commissioning of three major subcontracts at its 85%-owned Lemphane kimberlite project, in Lesotho, aimed at advancing the project towards an inferred resource status.

Multidisciplinary mining consultancy Paradigm Project Management has been appointed to undertake the scoping study to design an operational model to support a mining lease application the company intended to submit to the Lesotho Department of Mines during the first quarter.

The study, which would be completed and delivered to the company by the end of February, included openpit mine designs, tailings and waste rock disposal options, as well as process plant design and capital and operating costs estimates.

Paragon reported that elements of this study were already at an advanced preparatory stage.

Further, the company has appointed drilling specialists Rodio Geotechnics to undertake a 2 000 m first-stage delineation drilling programme to a maximum depth of 400 m to determine the internal structure and dimensions of the kimberlite body.

This programme would be followed by a more extensive 3 000 m campaign later this year to accurately delineate the kimberlite.

The drilling equipment was due to be mobilised and drilling expected to start later this month.

In addition, engineering and project management consultancy Amec was commissioned to deliver a full geological model of the Lemphane kimberlite, undertaking surface mapping and core logging.

The study programme was expected to start in February and continue for several months to deliver a clear understanding of the internal structure of the kimberlite with regard to geology and grade distribution, which, on completion, would be integrated with the geology mapped at surface and the surface bulk sampling results. 

The ultimate objective was a well-constrained resource in three dimensions, yielding reliable tonnage, grade and ore value data.

“The scoping study, drilling contract and geological modelling work programme, in conjunction with the company’s ongoing bulk sampling programme, will enable us to determine the economic potential of our flagship project,” Paragon MD Stephen Grimmer said in a statement.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION