Nimba mine, Liberia

20th March 2015

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

  

Font size: - +

Name: Nimba mine.

Location: The Nimba iron-ore deposit is located in the far north-west of Liberia, close to the border junction with Guinea and Côte d’Ivoire.

Controlling Company: Sable Mining.

Brief History: Sable Mining acquired the interest in Nimba in February 2012 through the group’s 80%-owned Guinean subsidiary, West Africa Exploration. The group initiated exploration activities at Nimba in March 2012 to assess the resource potential of the project and demonstrate its viability for commercial production in the near term. A preliminary feasibility study completed on the project in March 2014 demonstrated a commercially attractive high direct shipping ore (DSO) grade iron-ore development project.

Brief Description: Nimba is a significantly new iron-ore discovery, demonstrating that it is one of the largest undeveloped on- or near-rail DSO projects not owned by the major mining companies in West Africa.

Geology/Mineralisation: Nimba’s high-grade iron-ore mineralisation occurs at surface. This surface mineralisation stems from the unique way in which the Nimba orebody evolved. Located at the base of a very steep mountain, Mount Nimba, the project’s plateaux was historically the subject of a high-energy environment within which noniron boulders were essentially smashed. The boulders eroded at the base, forming high-grade canga in deep palaeo-channels.

Resources: Total Joint Ore Reserves Committee resources as at February increased from 181.8-million tonnes at an in situ grade of 58.8% iron to 205.2-million at average in situ grade of 57.8%, both were estimated at an iron cutoff of 40%.

Products: The mine will produce a high-grade iron (60% to 63%) DSO product.
Mining Method: Openpit and truck and shovel mining from multiple openpits for selective mining and blending.
Major Infrastructure and Equipment: The proposed mine will comprise two mobile plants to produce three-million tonnes a year of lump and fines DSO product.
It is envisaged that a simple dry plant process, involving crushing and screening will produce a high-grade lump product in the early stages of production followed by the introduction of a wet process, which will be fully able to produce a high-grade lump and fines product.

Prospects: A full bankable feasibility study is expected to be published in the first quarter of 2016, which will also include infrastructure development requirements in Liberia.

Contact Person: Andrew Groves

Contact Details:
Sable Mining Africa,
tel +44 20 7408 9200,
email info@sbmf.co.uk, and
website www.sablemining.com.

Edited by Leandi Kolver
Creamer Media Deputy Editor

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION