New Gold shuts Rainy River mill to manage water buildup

2nd May 2019

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Intermediate gold producer New Gold has shut down the mill at its Rainy River mine to manage excess water that has built up as a result of a rapid spring melt and large snow pack in northern Ontario, but the temporary shutdown is not expected to impact on its production guidance.

The mill was shut down on April 24 to expedite the pumping of about 700 000 m3 of excess water from the tailings management area to the water management pond and should be fully operational again within five days, New Gold said on Wednesday.

Mining and crushing operations had not been impacted and ore was being stockpiled for processing when the mill restarted.

The company also took advantage of the shutdown by accelerating maintenance work.

“Management is addressing the issue of excess water appropriately and in a manner that is consistent with our commitment to protecting our environment. We remain focused on executing our current mine plan and are confident that the mill will resume normal operations soon,” stated CEO Renaud Adams.

Rainy River is forecast to produce between 250 000 oz and 275 000 gold-equivalent ounces (GEO) this year. In the first quarter, the mine delivered 62 278 GEO – a significant improvement on the year-earlier performance of 40 016 GEO.

New Gold also owns the New Afton mine, in Canada, and the Cerro San Pedro mine in Mexico, as well as the Blackwater project in Canada.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION