Molo Phase 1 construction budget increased by $3m; construction starts on hybrid power plant

25th May 2022

By: Creamer Media Reporter

     

Font size: - +

TSX-listed NextSource Materials says increases in global logistics costs have resulted in a $3-million increase in the construction budget for Phase 1 of the Molo graphite mine, in Madagascar.

The Phase 1 capital cost budget is now $24-million, plus a further $3-million for working capital.

Earthworks and civil construction at the mine site are progressing on schedule and will be ready for the arrival of the processing plant and auxiliary buildings in June, the company reports.

Completion of construction and plant commissioning is expected in the third quarter of this year.

Further, the Madagascar subsidiary of CrossBoundary Energy (CBE) has started construction of the solar and battery hybrid power plant for Phase 1 of the Molo mine.

NextSource in November 2021 announced that it had appointed CBE to build, own and operate a solar, battery and thermal hybrid energy power plant over a 20-year term.

The plant will consist of a 2.6 MW solar photovoltaic facility, a 1 MWh battery energy storage system (BESS) and a 3.1 MW thermal facility, comprising diesel generators. The plant will be located adjacent to the Molo mine site and will provide up to 33% of the mine's Phase 1 electricity needs from renewable solar energy, with the remainder to be provided by the diesel generators.

NextSource and CBE plan to optimise the solar component throughout the contract to increase the percentage of renewable energy available to the mine.

The thermal facility, solar facility and BESS are all expected to be installed and operational prior to initiating commissioning of the Molo processing plant.

"The solar facility and battery energy storage system is integral to our commitment to minimise our carbon emissions and build a sustainable mine. Over the life of the project, we will aim to further reduce our reliance on fossil fuels, with the added benefit of lower costs and, therefore, better project economics," NextSource president and CEO Craig Scherba comments.

 

 

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION