https://www.miningweekly.com

Los Pelambres expansion to cost extra $400m, says Antofagasta

20th January 2021

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Chile copper miner Antofagasta has revised the capital cost estimate for its Los Pelambres expansion project to $1.7-billion, from the original guidance of $1.3-billion, mainly owing to revised marine works.

The project, which will add about 60 000 t/y to the mine’s production, will be completed early in the second half of next year, the London-company said on Wednesday, stating that Covid-19 restrictions had impacted on the schedule.

The project would continue with only 75% of the originally planned on-site manpower to comply with Covid-19 restrictions. Construction work at the project was suspended for several months in 2020.

About $235-million of the revised cost estimate relates to changes to the marine works that were needed to enable the future expansion of the desalination plant.

Antofagasta said that the Los Pelambres expansion was 45% complete at the end of December.

Meanwhile, the company reported production of 733 900 t of copper in 2020, which was in line with its guidance and 4.7% lower than the record production in 2019. Fourth-quarter output was 192 600 t.

The miner also produced 54 700 oz of gold and 3 700 t of molybdenum in the final quarter of 2020.

Net cash costs for the full year were below guidance at $1.14/lb.

Group production in 2021 is expected to be 730 000 t to 760 000 t of copper, 240 000 oz to 260 000 oz of gold and 9 500 t to 11 000 t of molybdenum.

Group cash costs in 2021 before and after by-product credits are expected to be at $1.65/lb and $1.25/lb, respectively.

Capital expenditure in 2021 is expected to be $1.6-billion, as the rate of expenditure on its growth projects accelerates following their temporary suspension in 2020, which deferred some $200-million into 2021, and higher costs at the Los Pelambres expansion project.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION