Labrador Iron says PEA supports plan to resume iron-ore production

10th March 2021

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Canada’s Labrador Iron Mines has completed a preliminary economic assessment (PEA) for its Houston project, located in the Labrador Trough region near Schefferville.

The results of the PEA support the company’s plan to resume iron-ore production with low restart capital of C$86.8-million and robust economics at a time when the global iron-ore markets are strong, says chairperson and CEO John Kearney.

The PEA calculates a net present value of C$109-million and an internal rate of return of 39%. A 36-month trailing average iron-ore price of $90/dmt, which is about 45% of the current market price, was used.

“At current market prices the Houston project will yield spectacular financial results,” says Kearney.

The study forecasts the production of two-million tonnes a year of high-grade (62%) direct shipping ore for 12 years.

The project consists of the Houston 1, Houston 2 and Houston 3 deposits located in Labrador and the adjacent Malcolm deposit located just over the provincial border in Quebec. The Houston 1 and Houston 2 deposits have been permitted and are considered ready for construction. The Houston 3 deposit and Malcolm deposit are planned to come on stream in the second half of the 12-year projected mine life, following permitting.

“The Houston project is considered ready for construction as the first stage deposits have already undergone extensive regulatory review and permitting approval. With an 18-month construction period, the Houston project has very low technical risk, with only a short gravel road and rail siding as the principal construction components,” says Kearney.

The project is expected to employ 297 people in total at its peak, with about 20% of the labour force sourced from local communities.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION