PERTH (miningweekly.com) – The Western Australian Department of Mines, Industry Regulation and Safety has approved gold miner Red 5’s mining proposal for the King of the Hills gold mine.

Red 5 on Tuesday said that all approvals to start construction of the processing facility is now in place, and the engineering, procurement and construction contractor, MACA, has mobilised to site and has stared earthworks in the process plant area.

“With final approval for the commencement of construction of the processing plant now in place, we have a hive of activity underway at King of the Hills, with bulk earthworks progressing and installation of the village well under way,” said MD Mark Williams.

“Major components of the mill are being manufactured or undergoing refurbishment and upgrade, putting all of our workstreams on track for achievement of first gold production from the four-million tonne a year King of the Hills bulk mining operation in the June quarter of 2022.”

The initial mine plan for King of the Hills estimated a mine life of 16 years, with gold production in years one to six expected to average 176 000 oz/y, while peak annual gold production of 203 000 oz/y will be achieved in 2024, benefitting from underground mining of one-million tonnes a year in years one to four.

 

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION