Jambreiro PFS proves up for Centaurus

5th July 2019

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – A prefeasibility study (PFS) into the Jambreiro iron-ore project, in Brazil, has estimated that the project would require a capital investment of A$59.8-million.

ASX-listed Centaurus Metals on Friday noted that the one-million-tonne-a-year operation is expected to have an initial mine life of 18 years, and would deliver high-grade, low-impurity sinter product.

The PFS estimated life-of-mine revenues of more than A$1-billion, and earnings before interest, taxes, depreciation and amortisation of A$533-million, with average annual operating cash flows anticipated at A$29.6-million.

The study estimated a post-tax net present value of A$114.9-million and an internal rate of return of 32%, based on a mine gate domestic iron-ore price of $41/t.

“The results of the 2019 PFS have confirmed that Jambreiro is a financially robust, long-life, development-ready project which is ideally placed to capitalise on the changed iron-ore market environment that has emerged both domestically in Brazil and internationally in the past six months,” said Centaurus MD Darren Gordon.

“The PFS clearly shows that Jambreiro is a quality project, with strong technical fundamentals and robust financial returns forecast from an initial 18-year mine life, based on the friable mineralisation only. The strong economics are underpinned by low operating cash costs, forecast at just A$29/t of final product, which reflect the low stripping ratio, the free-digging nature of the friable material, and the extent of natural liberation of the ore.”

Gordon on Friday said that while a detailed bankable feasibility study (BFS) would be required to advance all elements of the Jambreiro project to a stage that could support debt financing, the company expected a large portion of the capital and operating costs included in the PFS would be rolled forward into the BFS without much more work, given the high level of confidence Centaurus had in the process flowsheet, and the cost of key capital and operating inputs.

“In parallel, we are advancing product offtake discussions with both domestic consumers and international export traders. The recent change in the supply dynamic, both domestically and internationally, is driving a strong and sustained demand for the Jambreiro product, and we are aiming to have agreements in place in line with the delivery of a bankable feasibility study.”

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION