Ivanhoe accelerates Kamoa-Kakula expansion to 7.6Mt/y

22nd September 2020

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Toronto-listed Ivanhoe Mines is accelerating its Kamoa-Kakula expansion in the Democratic Republic of Congo to prepare for an expected surge in copper demand that will outstrip supply.

The expansion of Kakula processing plant from 3.8-million tonnes a year to 7.6-million tonnes a year would be brought forward from the first quarter of 2023 to the second quarter of 2022, the company announced on Monday.

In order to accelerate, the Kamoa-Kakula joint venture would order long-lead items with a total commitment value of $100-million within the coming weeks, of which an estimated $25-million would be spent this year.

"There are many smart people in the mining industry who strongly believe that copper is quickly approaching a supply and demand divergence; where the amount of copper being produced globally will be far outstripped by demand," said co-chairperson Robert Friedland. "As such, we want to ensure that the Kamoa-Kakula operation reaches its near-term production potential as expeditiously as possible, while also maintaining our strong balance sheet."

"Getting into the queue now for the critical long-lead-time items, such as the ball mills, costs very little up-front money and enhances our flexibility to quickly move ahead on the first of multiple planned expansions."

A recent prefeasibility study for the expanded 7.6-million-tonne-a-year mining operation - sourcing ore from both the Kakula and Kansoko mines - outlines an after-tax net present value, at a 6% discount, of $6.6-billion and an internal rate of return of 69% over a 37-year mine life, as well as payback of 2.5 years.

The economic model assumed a copper price of $3.10/lb, but Friedland pointed out that at least one major global investment bank was forecasting prices ranging from $3.20/lb to $3.60/lb over the next six to 12 months, based on its view that a supply deficit would form in 2021.

Ivanhoe further reported that construction of Kakula's initial 3.8-million-tonne-a-year processing plant was well under way, with the remaining long-lead items already delivered to site, with the exception of the transformers, which were expected in October.

Kakula is projected to be the world's highest-grade major copper mine with an estimated average ore feed grade of 6.6% copper over the first five years of operation, and 6.2% copper over the first 10 years.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION