Integra goes for heap leach only option at DeLamar

22nd April 2022

By: Creamer Media Reporter

     

Font size: - +

TSX-V- and NYSE American-listed Integra Resources has announced that it is advancing the heap-leach stage of its DeLamar project, in Idaho, into permitting and development on a standalone basis.

The company stresses that the low-cost, low-risk strategy to focus on the financial engine of the project – the heap leach – does not negate the strong optionality of the project in multiple areas.

“Integra’s 2022 DeLamar PFS [prefeasibility study] highlighted an abundance of optionality derived from a myriad of development scenarios to advance the asset,” says president and CEO George Salamis.

Based on data provided in the PFS, and despite the fact that the project was costed out during a period of high inflation, the heap-leach operation at DeLamar showed solid returns with an after-tax net present value, using a 5% discount, of $314-million and an after-tax internal rate of return of 33% at $1 700/oz gold and $21.50/oz silver.

The heap-leach operation will produce about one-million ounces of gold equivalent on its own.

During the eight-year heap-leach operation, the project averages 136 000 oz/y of gold equivalent with site-level all-in sustaining costs (AISC) of $814/oz.

The heap-leach standalone strategy will result in total project capital savings of more than $235-million and a decrease in site-level AISC of 15%, Salamis notes.

"The strategy also simplifies the future permitting, financing and construction plans since permitting and financing the heap leach as a standalone mine without the mill initially, is viewed as a lower-risk strategy. When fully developed, DeLamar has the potential to become one of the lowest cost and largest heap-leach mining operations in North America that is not currently owned by a major producer,” he says.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION