https://www.miningweekly.com

Honeymoon fully permitted for a restart

4th May 2021

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – A review has confirmed that ASX-listed Boss Energy has all the required permits to restart uranium production at its Honeymoon project, in South Australia.

The company on Tuesday reported that all federal and state permits required to mine, process, store, transport and export uranium from the Honeymoon operation had been received, along with permits needed to increase the nameplate production capacity to 2.45-million pounds a year.

Boss MD Duncan Craib told shareholders that the soon-to-be-completed enhanced feasibility study on the Honeymoon project would provide a roadmap to re-commissioning with simplified modifications.

“Combined with a significant uranium stockpile locked in at attractive prices and all the required approvals and permits for near-term production in place, Boss is well on track to be Australia’s next uranium producer.

“We will now complete the enhanced feasibility study in the coming weeks, paving the way for binding offtake contracts and a clear pathway for the restart of production, thereby capitalizing on Boss’ first-mover advantage in the new uranium cycle.”

A 2020 feasibility study into the Honeymoon project estimated that it would require a capital investment of $63.2-million to restart operation, and that the project would generate more than A$492-million in pre-tax free cash flow over the 12-year mine life, while the net present value had been estimated at $163-million and the internal rate of return at 42.9%.

Stage 1 of the operation was based on the refurbishment of the existing solvent extraction plant, with significant process improvements, while Stage 2 consisted of the addition of an ion exchange circuit, to achieve an annual production of two-million pounds of uranium oxide equivalent.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION