First gold from Alamos’ La Yaqui Grande mine

20th June 2022

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Canada-based Alamos Gold has announced initial gold production from the La Yaqui Grande mine, in Mexico, following the completion of construction this month.

Stacking rates continue to ramp up with leaching activities beginning earlier in June.  

Completing construction ahead of schedule while navigating a challenging environment over the past few years with Covid-19 was a significant achievement, said CEO John McCluskey on Monday.

First announced in July 2020 as Alamos' next low-cost, high-return project in the Mulatos district, this large-scale construction project will extend the life-of-mine for at least five years thus sustaining the company’s presence and importance in the production of gold in the state of Sonora.

“Given its higher grades and recoveries, La Yaqui Grande underpins a strong outlook for Mulatos with higher production and lower costs driving growing free cash flow in the second half of this year and beyond,” McCluskey added.

A total of 991 oz of gold were produced from the initial pour. La Yaqui Grande is expected to produce about 3 000 oz in June which is already factored into second quarter consolidated production guidance of between 100 000 oz and 110 000 oz of gold.

Consistent with full-year 2022 guidance, stacking rates at La Yaqui Grande were expected to ramp up through the second half of the year driving production higher and costs lower at Mulatos and company-wide starting in the third quarter.

Combined with lower capital spending, with construction of La Yaqui Grande completed Mulatos is expected to generate strong mine-site free cash flow starting in the second half of the year. Costs are expected to continue to improve into 2023 reflecting a full year of production from La Yaqui Grande.

La Yaqui Grande generated more than 1 000 jobs during the construction phase and would continue to sustain 450 direct jobs.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION