European Lithium publishes Wolfsberg PFS results

5th April 2018

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – The Wolfsberg lithium project, in Austria, is expected to deliver about 620 000 t/y run-of-mine production over a 12-year period, ASX-listed European Lithium reported on Thursday.

A prefeasibility study (PFS) has estimated that the concentrator will produce an average of 55 400 t/y of spodumene concentrate, with an average of 114 000 t of feldspar and 71 000 t of quarts as by-products.

European Lithium noted that it planned to convert the lithium in the spodumene concentrate to an average of 8 400 t/y of lithium hydroxide monohydrate at a hydrometallurgy plant to the south of the mine.

The company said that with some added equipment and improved scheduling, the mining rate could be increased to around 720 000 t/y, which resulted in a mine life of ten years.

The 20% increase in the processing rate will result in lithium hydroxide monohydrate production increasing to an average of 10 129 t/y. The accelerated production rate will increase project capital from $388.6-million considered in the base case, to $423.6-million.

The base case production scenario is estimated to have a pre-tax net present value (NPV) of $263.2-million and an internal rate of return (IRR) of 21.2%, while the accelerated option has a NPV of $339.4-million and an IRR of 25.6%.

European Lithium chairperson Tony Sage said on Thursday that the completion of the PFS, which established the technical and economic viability of the Wolfsberg project, was a major step in the project’s development.

“The company will endeavor to formally start the definitive feasibility study in July, with the aim of completing it before the end of 2018,” Sage said.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION