Euro Sun explains its ‘environmentally responsible’ Romania gold project

9th April 2019

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Canada-based Euro Sun Mining has explained its decision to design its Rovina Valley gold project, in Romania, as a so-called “green” gold project, without the use of wet tailings facilities and cyanide.

In a statement addressing “many questions” from shareholders following the February release of a preliminary economic assessment (PEA), Euro Sun CEO Scott Moore said on Monday that the company had opted for a “better environmentally and socially responsible project”, rather than to “just maximise profitability”.

Euro Sun acknowledged that Rovina Valley would have had a lower capital budget and lower operating costs, if a traditional wet tailings facility were to be built. Using cyanide in a closed circuit would have generated higher recoveries, therefore, higher tax revenues for government.

Initial capital expenditure for the Phase 1 development, which is based on producing 108 000 oz/y gold and 13.3-million pounds a year of copper, is estimated at $339-million.

“Rovina Valley is a clear example of a project that meets today’s investor mandate for environmental social governance companies in which to invest,” said Moore.

He added that the decision to stay clear of wet tailings and cyanide was a “conscientious” one and was made jointly by the company and the government of Romania.

The current PEA updates a study of nine years earlier, which had outlined a larger-scale operation than the phased approach currently planned. The initial PEA would have involved the simultaneous exploitation of both openpit deposits – Colnic and Rovina.

The 2019 PEA is based on only exploiting the Colnic deposit, but includes the 20 000 t/y dry stack tailings processing facilities that will be used in treating ore from both deposits.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION