Eastplats achieves first PGM recoveries from tailings project

18th February 2020

By: Marleny Arnoldi

Deputy Editor Online

     

Font size: - +

JSE- and TSX-listed Eastern Platinum (Eastplats) has successfully produced platinum group metal (PGM) concentrate from its refurbished small-scale PGM Circuit D – previously called the scavenger plant circuit.

The company is using feed from its retreatment project, located at the company’s Crocodile River mine, in South Africa, following the recovery of chrome concentrate.

The PGM Circuit D plant is able to process 40 000 t of feed a month and the construction costs were less than $150 000, as the company used existing infrastructure that was on care and maintenance at the mine.

“This is the first step in the company’s full-scale assessment of the PGM recoverability of the tailings resource and provides further revenue opportunities for Eastplats.

“The company will continue to move forward with its assessment of the larger PGM recoverability opportunities in relation to the tailings resource,” says Easplats president and CEO Diana Hu.

Meanwhile, Eastplats produced 598 034 t of chrome concentrate from its retreatment project, with an average 38.6% chromium(III) oxide grade. 

During January, the company produced an additional 101 606 t of chrome concentrate from the retreatment project, which was the best monthly production to date.

Going forward, Eastplats will invest about $6-million in additional equipment to enhance its chrome concentrate recovery.

The financing of the upgrade has been agreed to in principle with Union Goal Offshore Solution on similar loan terms to those contained in a previously signed framework agreement.

The company entered into a framework agreement with Union Goal in March 2018 around the construction, re-mining and processing of a tailing resource and offtake of chrome concentrate from Barplats Mines’ tailings facility – or the retreatment project – located at the Crocodile River mine.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION