Cyprium eyes 2023 start at Nifty

31st May 2022

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Copper hopeful Cyprium Metals is hoping to produce its first copper metal plate from its Nifty operations by the second half of 2023.

The ASX-listed company on Tuesday said that project financing for the restart of the Nifty operations, in Western Australia, was advancing with financiers.

For the debt portion of the Nifty copper project restart, Cyprium is targeting A$240-million to A$260-million of total debt funding, including cost overrun contingency and working capital, for the financing of the Nifty restart and project costs, which is expected to comprise senior secured financing, subordinated debt and offtake financing.

“The Nifty copper project restart study demonstrates that the fundamentals of the project are robust, which does not include the increased mineral resource estimate that we announced earlier this month,” said Cyrpium MD Barry Cahill.

“We are currently focused on finalising the project debt financing for a fully funded project and then to execute our construction plans so that we produce copper metal plate on site in the second half of 2023.

“While working through the finance process, Cyprium has not been idle, continuing to set Nifty up for the construction works post-finance and pushing forward with the Maroochydore and Murchison projects as assay results are received from the 2021 field season.”

The Nifty restart study estimated that Cyprium would require a capital injection of A$149-million, and could produce  25 000 t/y of copper cathode.

The restart is focused around the first phase of heap leach retreat and oxide openpit, and it is envisaged that the life will extend to the sulphide stage of the openpit with a considerably larger resource available.

The sulphide study has already commenced, with design optimisation and metallurgical testwork currently being undertaken.

Oxide cathode production will reach 146 100 t of metal, with the oxide mine life estimated at just over six years, between 2023 and 2029, with a sulphide potential of more than 20 years.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION