Citronen lead/zinc project, Greenland

30th July 2021

By: Sheila Barradas

Creamer Media Research Coordinator & Senior Deputy Editor

     

Font size: - +

Name of the Project
Citronen lead/zinc project.

Location
North-east Greenland.

Project Owner/s
Ironbark Zinc.

Project Description
A bankable feasibility study (BFS) has shown Citronen to have robust economics. The 2021 BFS represents the first ground-up evaluation of the project in a decade and supersedes the feasibility study published in September 2017.

The 3.3-million-tonne-year operation has a significantly expanded ore reserve of 48.8-million tonnes grading 4.8% zinc and 0.5% lead. Mineral resources are estimated at 85-million tonnes grading 4.7% zinc and 0.5% lead.

The openpit and underground operation will treat an average grade of 4.7% zinc and 0.5% lead over an initial 20-year mine life.

The mine schedule has been optimised to prioritise zinc grade in the early years of production, with the highest-grade zone – Beach Zone – being prioritised for milling. Feed from the underground operation will be supplemented with ore from the Discovery openpit.

Waste rock generated during the initial development of the openpit and underground operations will be used as fill for construction purposes, while an openpit ore stockpile will be generated ahead of the start of processing.

The updated flowsheet for the project processing circuit involves crushing, dense-medium separation, milling and a flotation circuit.

The project has shown substantial exploration upside.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an after-tax net present value, at an 8% discount rate, of $363-million and an internal rate of return of 15.2%.

Capital Expenditure
Capital expenditure has increased from $514-million in the 2017 BFS to $654-million in the 2021 BFS.

Planned Start/End Date
Not stated.

Latest Developments
Ironbank plans to start the formal project financing process with US Exim Bank shortly.

Environmental, social and governance approvals, and management plans, are well advanced.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Ironbark Zinc, tel +61 8 6146 5325 or email admin@ironbark.gl.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION