CIMIC settles contract dispute with JKC Australia

13th April 2022

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – Services provider CIMIC has agreed to a A$492.5-million settlement in a contract dispute at the Ichthys liquefied natural gas (LNG) project, in the Northern Territory.

CIMIC, along with consortium partners Ch2M Hill Australia and General Electric Company, was in 2012 contracted by JKC Australia to carry out design, construction and commissioning work of a combined cycle power plant at the Ichtys project.

In early 2017, the consortium terminated the contract and commenced arbitration proceedings. The arbitration hearings were scheduled to start this week, but CIMIC has announced that it had entered into a conditional, and confidential, agreement with its consortium partners and JKC, resulting in the settlement of all matters relating to the contract.

CIMIC told shareholders that it would pay A$192.5-million in April this year, and a further A$300-million in March of next year, as its contribution to the settlement amounts.

The settlement agreement is subject to a number of conditions precedent related primarily to payment obligations, which are expected to be satisfied this month. Until the conditions precedent are satisfied, the arbitration will continue.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION