Calidus progresses Warrawoona ramp-up

4th July 2022

By: Darren Parker

Creamer Media Contributing Editor Online

     

Font size: - +

ASX-listed Calidus Resources poured 8 916 oz of gold in the June quarter during the commissioning and ramp-up of the Warrawoona gold project in the Pilbara Goldfield of Western Australia, with an additional 1 192 oz of gold in circuit.

The quarter saw the first gold poured in May following the processing plant commissioning being completed.

 A total of A$22-milllion was received from gold sales during the quarter.

The gold produced to date reconciled the resource model and grade control model and resulted in the first debt repayment of A$3-million made to financial services provider Macquarie Bank as scheduled.

Milling rates progressed throughout the quarter and were expected to reach the nameplate capacity of 2.4-million tonnes a year this month. Calidus reported a total of 327 000 t of low grade ore, commissioning ore and run-of-mine ore milled during the quarter.

The process plant was tested at up to 2.8-million tonnes a year, with no major bottlenecks identified, Calidus said.

Mining has rapidly progressed in the past few weeks, with 20 000 bank cubic metres (BCM) a day movement achieved, against an average requirement of 18 500 BCM/d. A new excavator and additional manning was to be mobilised this month to ensure that the BCM movement was maintained.

Meanwhile, liquefied natural gas storage vessels were delivered to site with a transition to gas-fired electricity expected this month.

Calidus reported a cash and cash equivalents position of A$19.8-million at end of June.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION