Australia Mines’ Sconi now a 30-year operation

13th June 2019

By: Esmarie Iannucci

Creamer Media Senior Deputy Editor: Australasia

     

Font size: - +

PERTH (miningweekly.com) – ASX-listed Australian Mines has updated the economics and mine plan for its Sconi cobalt/nickel/scandium project, in Queensland.

The company on Thursday said that Sconi’s projected mine life has increased from the 18 years considered in the bankable feasibility study (BFS), to 30 years, on the back of a 69% increase in the ore reserve, which now stood at 57.3-million tonnes.

In light of the updated ore reserve, Australian Mines also developed new pit designs for both the Greenvale and Lucknow ore, while maintaining its design for the Kokomo pit.

Sconi is now expected to produce more than 1.4-million tonnes of nickel sulphate, 209 000 t of cobalt sulphate and 1 441 t of scandium over its mine life, producing an average of 46 800 t/y of nickel sulphate and 7 000 t/y of cobalt sulphate based on a two-million-tonne-a-year operation.

The additional mine life has increased the projected life-of-mine revenue by 44%, to A$13.3-billion, while total free cash flow projections have increased by 93%, to A$5-billion.

The project’s pre-tax net present value has also increased by 12% on the BFS, to A$1.47-billion, while the pre-tax internal rate of return has been estimated at 20%.

Capital costs for the project have been maintained at $974-million, with total C1 cash costs net of cobalt and scandium estimated at $1.46/lb of nickel.

Australian Mines MD Benjamin Bell on Thursday said that the additional tonnage at Sconi formed the basis of the revised mine plan and the ongoing refinement to the company’s BFS, with the company continuing work to maximise value for shareholders.

The Sconi project was declared a prescribed project by the Queensland government earlier this year, with Australian Mines committing to providing opportunities for local residents and businesses.

Some 500 staff will be employed at Sconi during construction, and once in production, the project would require a staff of 300 people.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION