Antofagasta raises capital cost estimate for Centinela concentrator

11th August 2022

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

London-listed miner Antofagasta has increased the capital cost for a new concentrator plant at its Centinela mine, in Chile, to $3.7-billion. This is a $1-billion increase on the 2015 prefeasibility study estimate of $2.7-billion and includes a new water system and design changes.

The company will decide by early 2023 if it is going to proceed with the expansion, which will increase production by an average of 170 000 t/y of copper-equivalent and move Centinela into the first cost quartile.

The Centinela project has two phases, the first of which will be the 95 000 t/d concentrator and the second a potential further expansion to 150 000 t/d of ore. The second phase will source ore initially from the recently opened Esperanza Sur pit and later from the Encuentro pit.

The Esperanza Sur pit contains 1.4-billion tonnes of reserves with a grade of 0.4% copper, 0.13 g/t gold and 0.012% molybdenum.

Antofagasta is considering outsourcing water supply for Centinela’s current and future operations. A tender process was started in late 2020 to invite third parties to provide water for the mine and the process is expected to be completed in the fourth quarter.

Antofagasta has also recently increased the capital cost estimate for Phase 1 of its Los Pelambres expansion from $1.7-billion to $2.2-billion. Of this increase, about $220-million was related to the impact of Covid-19 on costs and the construction schedule and $170-million to general inflation.

Edited by Creamer Media Reporter

Comments

The functionality you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION