Alkane updates Dubbo business case

4th June 2018

By: Mariaan Webb

Creamer Media Senior Deputy Editor Online

     

Font size: - +

Multi-commodity miner and explorer Alkane Resources has completed the engineering and financial review of its zirconium, niobium, hafnium and rare-earth project near Dubbo, in New South Wales, which confirmed that the project is technically sound and financially viable, generating a potential A$4.7-billion in free cash flow over its mine life.

The review, which follows a 2015 front-end engineering design study, is intended to sharpen negotiations with industry participants and funding partners in Australia, Japan, Korea, the US, Europe and China to enhance prospects for a project start.

The Dubbo project will cost between A$1.23-billion and A$1.5-billion, depending on which development option Alkane settles on.

The update is working on an one-million-tonne-a-year plant feed rate, which is its base case, and on a staged development of 500 000 t/y each.

The base case is forecasting capital expenditure of A$1.297-billion with an additional A$124-million sustaining capital over the 20 years of operational life, giving the project a net present value (NPV) of A$1.23-billion and an internal rate of return (IRR) of 17.5%.

The development will require A$808-million for Stage 1 and A$692-million for Stage 2, with sustaining capital of $39-million. This scenario delivers a NPV of A$909-million and an IRR of 16.1%.

Alkane has engaged Sumitomo Mitsui Banking Corporation to provide financial advisory services and to assist with arranging debt financing for the project. The company would appoint equity capital market specialist advisers to assist with the equity component of the required funding.

Alkane stated on Monday that formal financing discussions would start once offtake contracts had sufficiently advanced.  

“The project review details the considerable body of technical work that has occurred on the Dubbo project.

“In an external environment of rising commodity prices, interest in the project’s products is increasing as global manufacturers look for both material sources and supply chains outside China,” said MD Nic Earner.

Edited by Creamer Media Reporter

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION