Technical due diligence on Kibaran’s Epanko project complete
JOHANNESBURG (miningweekly.com) – After securing $2-million through a share placement earlier this year, in conjunction with additional funding mechanisms, junior graphite developer Kibaran Resources announced on Tuesday that technical due diligence on its Tanzania-based Epanko graphite project is now complete, making Kibaran the first ASX-listed company to undergo banker’s due diligence for a graphite project in Africa.
Independent engineering firm SRK was appointed by KfW IPEX-Bank to conduct technical due diligence as part of the bank’s senior debt financing due diligence on Epanko.
Kibaran noted that the Independent Engineer’s Report (IER) was considered the key aspect of KfW IPEX-Bank’s rigorous approval process for an up to $40-million senior debt facility for the development of the project.
SRK had now submitted its final IER to KfW IPEX-Bank, which was accompanied by a detailed action plan to address the recommendations that had been identified.
Having now confirmed the bankable status of the Epanko feasibility study, prepared by GR Engineering, KfW IPEX-Bank was now reviewing the IER to prepare for the submission of the UFK Guarantee application.
The IER focused on the Epanko bankable feasibility study (BFS) and the associated financial model. It also involved detailed analysis of the BFS including the geology, mining, metallurgy, process test work, pilot plant work, capital and operating costs, pricing and the financial model. The review also assessed all project-related risks and included a site visit to Epanko at the end of January.
Kibaran said the IER would be forwarded to Nedbank, Africa’s largest investment bank, which indicated interest in providing senior project debt financing of up to $30-million, alongside KfW IPEX-Bank.
“We are gratified with the calibre of this banking syndicate [which] is in accord with our strategy of securing blue chip offtake and financing partners for the Epanko project,” commented Kibaran chairperson Bob Pett.
Comments
Press Office
Announcements
What's On
Subscribe to improve your user experience...
Option 1 (equivalent of R125 a month):
Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format
Option 2 (equivalent of R375 a month):
All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors
including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.
Already a subscriber?
Forgotten your password?
Receive weekly copy of Creamer Media's Engineering News & Mining Weekly magazine (print copy for those in South Africa and e-magazine for those outside of South Africa)
➕
Recieve daily email newsletters
➕
Access to full search results
➕
Access archive of magazine back copies
➕
Access to Projects in Progress
➕
Access to ONE Research Report of your choice in PDF format
RESEARCH CHANNEL AFRICA
R4500 (equivalent of R375 a month)
SUBSCRIBEAll benefits from Option 1
➕
Access to Creamer Media's Research Channel Africa for ALL Research Reports on various industrial and mining sectors, in PDF format, including on:
Electricity
➕
Water
➕
Energy Transition
➕
Hydrogen
➕
Roads, Rail and Ports
➕
Coal
➕
Gold
➕
Platinum
➕
Battery Metals
➕
etc.
Receive all benefits from Option 1 or Option 2 delivered to numerous people at your company
➕
Multiple User names and Passwords for simultaneous log-ins
➕
Intranet integration access to all in your organisation