https://www.miningweekly.com
Financial|Gold|Infrastructure|PROJECT|Resources|Surface|Infrastructure
Financial|Gold|Infrastructure|PROJECT|Resources|Surface|Infrastructure
financial|gold|infrastructure|project|resources|surface|infrastructure

Pan African confident of meeting upper end of full-year production guidance

Pan African CEO Cobus Loots

Pan African CEO Cobus Loots

9th May 2024

By: Creamer Media Reporter

     

Font size: - +

South African gold producer Pan African Resources has revised its full-year production guidance to between 186 000 oz and 190 000 oz, compared with previous guidance of 180 000 oz to 190 000 oz, while maintaining its all-in sustaining cost guidance at between $1 325/oz and $1 350/oz.

In an update to shareholders about the group's production expectations for the full financial year to end June 30, it says it ceased processing of marginal surface sources at Evander Gold Mines during the second half of the financial year, as the processing of this material was becoming uneconomical.

It points out that the processing of the marginal surface sources at Evander contributed 2 500 oz to production in the first half of the financial year and that, if production from these sources is maintained throughout the second half of the financial year, group output will exceed 190 000 oz for the full-year.

"We are pleased that Pan African will achieve the upper end of our full-year production guidance, and would have exceeded guidance had we continued with the processing of surface material at Evander in the second half of the financial year. The robust production results, combined with record rand gold prices, should see the group deliver an excellent financial performance for the year," CEO Cobus Loots comments.

Pan African has, meanwhile, set its production guidance for 2025 at between 215 000 oz and 225 000 oz.

MTR PROJECT ON TRACK
Pan African further reports that its Mogale Tailings Retreatment (MTR) project remains on schedule for commissioning and steady-state production in December. The company also does not expect any expenditure overruns for the project.

The company has updated the project's financial model to include the latest operating cost and production estimates, forecast rand:dollar exchange rate and dollar gold price.

The updated model is based on an exchange rate of R19 to the dollar, compared with the R15.50 to the dollar used in an earlier definitive feasibility study (DFS), while the gold price forecast has increased to $2 200/oz, compared with the $1 750/oz used in the DFS.

As a result of these changes, the project's pre-tax net present value (NPV) has increased to $183-million, from $63-million in the DFS, while the ungeared real internal rate of return has increased to 41.7%, from 20.1% in the DFS.

The payback on upfront capital investment of about $135.1-million has reduced to about two years, compared with the three-and-a-half years estimated in the DFS.

Further, Pan African in March completed an internal prefeasibility study (PFS) for the Soweto Cluster resource, which forms part of the MTR project.

The PFS considered numerous options, with the most feasible being the development of remining, overland piping and pumping infrastructure at the Soweto cluster resource to process the material at the MTR plant, Pan African notes.

It shows that the addition of the 110-million-tonne Soweto Cluster mineral resource has the potential to increase MTR production to about 60 000 oz/y over a 21-year LoM. A total additional capital requirement of $113-million will be required, with about $83-million to be incurred from year four to six and $29-million in year ten of the MTR's operation.

At a gold price of $2 200/oz and an exchange rate of R19 to the dollar, the pre-tax NPV combined for the Mogale and the Soweto Cluster is $283-million, representing an increase of $96-million, relative to Mogale's updated standalone financial model.

Pan African says it will now proceed with the necessary permitting and servitudes required for the remining and processing of the Soweto Cluster, with a final investment decision in due course.

"Our MTR project remains on schedule and on budget, and we look forward to commissioning it later in 2024. We have now demonstrated that the addition of the Soweto Cluster resources further improves the economic attractiveness of this world-class project," Loots says.

Edited by Chanel de Bruyn
Creamer Media Senior Deputy Editor Online

Comments

Showroom

Werner South Africa Pumps & Equipment (PTY) LTD
Werner South Africa Pumps & Equipment (PTY) LTD

For over 30 years, Werner South Africa Pumps & Equipment (PTY) LTD has been designing, manufacturing, supplying and maintaining specialist...

VISIT SHOWROOM 
Rentech
Rentech

Rentech provides renewable energy products and services to the local and selected African markets. Supplying inverters, lithium and lead-acid...

VISIT SHOWROOM 

Latest Multimedia

sponsored by

On-The-Air (17/05/2024)
On-The-Air (17/05/2024)
17th May 2024 By: Martin Creamer
Magazine round up | 10 May 2024
Magazine round up | 17 May 2024
17th May 2024

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION







sq:0.182 0.225s - 90pq - 2rq
1:
1: United States
Subscribe Now
2: United States
2: