Zimbabwe-focused mineral explorer African Consolidated Resources on Wednesday reported that it has concluded a processing contract with subsidiaries of project manager, TWP, for the production of gold from a sulphide concentrate dump, at the Pickstone project.
The sulphide concentrate dump contains an estimated resource of 28 300 oz gold, or 200 000 t at a 4,4 g/t, and production was planned to start in April or May 2010, to achieve full production by June 2010. An initial throughput of 20 000 t/m of ore was planned. |