Tuvatu alkaline gold project, Fiji – update

13th October 2023 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Tuvatu alkaline gold project, Fiji – update

Photo by: © Creamer Media

Name of the Project
Tuvatu alkaline gold project.

Location
On the island of Viti Levu, in Fiji.

Project Owner/s
Lion One.

Project Description
The project has demonstrated robust economic potential for a low-cost, high-grade gold operation with low upfront capital costs.

The project has an indicated resource of 1.01-million tonnes grading 8.5 g/t of gold and an inferred resource of 1.33-million tonnes grading 9 g/t of gold.

The updated PEA states the project’s gold production capacity at an average rate of 78 000 oz/y, at 8.6 g/t gold over a five-year mine life for a total of 331 300 oz.

Lion One plans to operate at an initial production capacity of 300 t/d before increasing the capacity to 500 t/d in mid-2024. The initial mining will focus on the near-surface resource while advancing underground development into high-grade mineralisation in Zone 500.

The processing plant will treat material using a two-stage crushing process, with a primary jaw crusher and secondary cone crusher feeding a two-stage grinding circuit.

The ground material will feed an integrated two-stage gravity concentration circuit, with some concentrates treated by an intensive cyanide leaching reactor and the remainder of the concentrates leached using conventional cyanide carbon-in-leach technology.

Gold will be recovered from the gold-laden carbon using conventional absorption-desorption recovery technology and smelted on site to produce gold doré bars.

The leached tailings will be treated using a sulphur dioxide/air process to remove any residual cyanide. Filtered tailings will be transported to Lion One’s tailings storage facility, 3.5 km from the Tuvatu mine site.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at a 5% discount rate, of $155.8-million and an internal rate return of 60.3%, with a payback of five years.

Capital Expenditure
The project has a capital expenditure of $66.8-million.

Planned Start/End Date
The company is fully funded to complete mine construction and bring the Tuvatu alkaline gold project into production by the end of 2023.

Latest Developments
Lion One Metals has poured its first gold. The project was completed ahead of schedule, with commissioning having started in September.

The mill is expected to ramp up to 300 t/d by the end of October 2023 and will reach a 500 t/d capacity by mid-2024.

Key Contracts, Suppliers and Consultants
None stated.