Name of the Project
Prieska copper/zinc project.

Location
Northern Cape, South Africa.

Project Owner/s
Diversified metal explorer and developer Orion Minerals.

Project Description
An updated bankable feasibility study (BFS) has confirmed the potential of Prieska to underpin a significant near-term, low-cost, copper/zinc development project, with exceptional opportunities for future growth.

The updated BFS on the foundation phase of the project proposes the development of a new 2.4-million-tonne-a-year copper/zinc mining operation at the brownfield project.

Underground and surface mining methods are planned to be used in conjunction with conventional froth-flotation concentration to produce differentiated copper and zinc concentrates for export.

Peak production is estimated at 23 000 t/y of copper and 88 000 t/y of zinc.

The life-of-mine (LoM) has been extended by two years, from 9.7 years to 11.5 years.

Material changes in the updated BFS, compared with the 2019 BFS plan, include:

The mining methods for the project remain unchanged, compared with those stated in the 2019 BFS. Tunnel development remaining from the previous mining operations allows for early access to underground production mining areas. A combination of longhole open stoping with fill and drift-and-fill mining methods are planned to be used, supported with paste backfill.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has a net present value, at an 8% discount rate, of A$779-million, compared with A$574-million in the 2019 BFS, and an internal rate of return of 39%, compared with 38% in the 2019 BFS. Payback from first production is estimated at 2.4 years, a decrease of five months.

Capital Expenditure
Market intelligence firm S2 Research noted in May 2022 that the peak funding requirement of Orion Minerals’ Prieska project had fallen from R2.4-billion to R2.25-billion. This has reduced the funding risk of the project.

In a prior note, S2 anticipated that Orion would need R2.7-billion to develop and optimise the Prieska mine.

Planned Start/End Date
Orion Minerals is targeting production startup in 2024, market conditions permitting.

Latest Developments
Orion Minerals has signed a definitive agreement for a R250-million convertible loan to advance the development of its Prieska project.

The agreement has been struck with the Industrial Development Corporation (IDC) of South Africa, under which the IDC will advance R250-million as a senior secured convertible loan facility to fund early works at the project.

The combined predevelopment funding being provided by Triple Flag and the IDC for Prieska now totals more than R371-million.

First drawdown from the IDC convertible loan and the A$10-million Triple Flag funding are expected in the first quarter of this year. 

This will provide funding for Orion to conduct demonstration trial mining and allow for dewatering to start from underground mine workings.

Both these workstreams are critical to Orion’s early works bankable feasibility study, which it expects to complete by mid-2023.

Orion flagged early production from the Prieska project at the start of 2022, rescheduling openpit mining to occur concurrently with the 33-month development phase of the Prieska Deeps mine, rather than at the end of the project life. This will enable Orion to capitalise on the near-term base metals market.

Key Contracts, Suppliers and Consultants
Companies involved in the BFS included A&B Global Mining; ABS Africa; BPDT & Co; Bluhm Burton Engineering & Ventilation Consultants; Beulah Africa; Cart Investments; DRA Projects South Africa; Earth Science Solutions; Endeavour Financial Limited; Falcon and Hume Attorneys Inc; Fraser McGill Mining & Minerals Advisory; Knight Piésold; METC Engineering; Gariep Mining and Exploration Services; Mets Consulting South Africa; Patterson and Cooke; PCDS Consultants; Power Plant Electrical Technologies; Professional Cost Consultants; Promethium Carbon; Shift Innovations; SRK Consulting; Strategy4Good; The MSA Group; Turnkey Civil (International) Group; VBKom Engineering Consultants; Whittle Consulting; and Z Star Mineral Resource Consultants.

Contact Details for Project Information
Orion Minerals, tel +27 11 880 3159 or email info@orionminerals.com.au.