Oyu Tolgoi underground mine project, Mongolia

19th July 2019 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Oyu Tolgoi underground mine project, Mongolia

Name of the Project
Oyu Tolgoi underground mine project.

Location
Mongolia.

Project Owner/s
Oyu Tolgoi is jointly owned by the Mongolia government (34%) and Turquoise Hill Resources (66%, of which Rio Tinto owns 51%). Rio Tinto has been managing the project since 2010.

Project Description
The Oyu Tolgoi openpit mine was completed on schedule in less than 24 months and production started in 2013. Since then, more than 440 000 t of copper have been sold.

About $6.4-billion has been invested to develop the openpit mine, concentrator and associated infrastructure, with an additional $500-million of capital costs for initial development of the underground mine.

The underground mine is expected to produce more than 500 000 t/y of copper, compared with current openpit production of 175 000 t/y to 200 000 t/y.

The mine also benefits from significant gold by-products, with an average gold grade of 0.35 g/t.

Underground production will come from the Hugo Dummett North deposit, including the North Extension, which contains probable ore reserves of 499-million tonnes, with an average grade of 1.66% copper and 0.35 g/t of gold.

The material from this brownfield expansion will use the existing concentrator and infrastructure.

The size and quality of this Tier-one resource provides additional expansion options, which could sustain production for many decades.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The project has an expected internal rate of return of more than 20%.

Capital Expenditure
The capital spend to bring the copper project into production is expected to range between $6.5-billion and $7.2-billion, an increase of between $1.2-billion and $1.9-billion, compared with the previous cost estimate of $5.3-billion.

Planned Start/End Date
Rio has also warned that first sustainable production from Oyu Tolgoi will be achieved only between May 2022 and June 2023, which is between 16 to 30 months later than the original feasibility study guidance in 2016.

Latest Developments
Rio is considering several mine design options for the Oyu Tolgoi project, after enhanced geotechnical information and data modelling suggested that there could be stability risks with the previously approved mine design.

These options are being evaluated to determine the final design of the first panel of mining, Panel 0, and this work is expected to continue until early 2020.

The miner has noted that given the further technical work that is needed, the definitive estimate, which will include the final estimate of cost and schedule for the remaining underground project, is now expected to be delivered in the second half of 2020, reflecting the preferred mine design approach.

The company will continue to focus on minimising the impact on the project schedule and cost as it works through the detailed analysis and testing of each mine design option.

Although further work is necessary to reach definitive conclusions, Rio is reviewing the carrying value of its investment in the project and will announce if any changes are required in the half-year results on August 1.

Key Contracts and Suppliers
Jacobs Engineering (EPCM) and Cimic Group’s Thiess (underground decline contractor).

On Budget and on Time?
Rio Tinto has warned of cost blow-outs and delays to its Oyu Tolgoi underground project.

Contact Details for Project Information
Rio Tinto media relations: Australia/Asia, Ben Mitchell, tel +61 3 9283 3620 or email media.enquiries@riotinto.com.
Turquoise Hill Resources investors and media, Tony Shaffer, tel +1 604 648 3934 or email tony.shaffer@turquoisehill.com.