Minim Martrap bauxite project, Cameroon

12th August 2022 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Minim Martrap bauxite project, Cameroon

Name of the Project
Minim Martrap bauxite project.

Location
Central Cameroon.

Project Owner/s
ASX-listed Canyon Resources.

Project Description
A bankable feasibility study (BFS) on Minim Martrap has been confirmed it as a robust long-term project. The project has an updated proven ore reserve of 108.91-million tonnes grading 51.1% total aluminium oxide and 2% total silica oxide. The project is expected to produce up to 6.4-million tonnes of high-grade bauxite a year over 20 years.

The low-strength ore and near-surface nature of the bauxite deposits support a conventional free-dig mining operation, using surface mining, with no drill and blasting required.

The bauxite recovered from the surface mining process does not require any additional processing. The surface miner crushes the ore to the required size as part of the mining process, after which the ore is exported.

The 20-year mining schedule represents only 10.6% of the current project resource, and technical studies have identified opportunities for a significant future increase in production tonnages.

Net Present Value/Internal Rate of Return
The project has a pretax net present value, at an 8% discount rate, of $452-million and an internal rate of return of 22%, with a payback of 4.1 years.

Capital Expenditure
Capital expenditure is estimated at $253.09-million, which includes the capital cost of the initial fleet of company-acquired rail rolling stock. The project will be funded through a combination of equity and debt financing.

Planned Start/End Date
Construction is expected to start in the second quarter of 2024, subject to regulatory approvals and financing.

Latest Developments
The company expects a final investment decision in the fourth quarter of 2022, subject to the timing of government approvals. Following the final investment decision, the engineering, procurement and construction contractor will be selected, with the front-end engineering design (FEED) to be selected within three months.

Critical long-lead time equipment, such as the locomotives and wagons, will be prioritised.

Further, several opportunities to improve capital costs and operating expenses have been identified in the BFS. Optimisation work will be undertaken to conclude these cost-saving opportunities before starting the FEED.

Key Contracts, Suppliers and Consultants
Resolve Mining Solutions (mineral reserve estimate).

Contact Details for Project Information
Canyon Resources, tel +61 8 6382 3342 or email info@canyonresources.com.au.