Gunnison copper project, US

20th September 2019 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Gunnison copper project, US

Name of the Project
Gunnison copper project.

Location
The project is located about 100 km east of Tucson, Arizona, in the US, on the south-eastern flank of the Little Dragoon mountains, in the Cochise mining district.

Client
Excelsior Mining Corp.

Project Description
The project has estimated resources of 873-million short tons of measured and indicated oxide and transitional mineral resources at a 0.05% total copper cutoff grade, as well as an inferred mineral resource of 187-million short tons.

Diluted mineral reserves are estimated at 782-million short tons of probable mineral reserves.

The project envisages development in three production stages, with capacities of 25-million pounds a year in Stage 1, 75-million pounds in Stage 2 and 125-million pounds a year in Stage 3.

The stages to ramp up production are meant to minimise capital at risk until the in situ recovery (ISR) process at the Gunnison project is better understood.

For Stage 1 operations, Excelsior will use the neighbouring Johnson Camp mine (JCM), which has a functional 25-million-pound-a-year solvent extraction-electrowinning (SX-EW) plant north of the Gunnison project wellfield.

In the current mine plan, Stage 2 production will start in Year 4 of the mine life and will use the JCM SX-EW plant, as well as a new 50-million-pound-a-year Gunnison SX-EW plant.

Stage 3 production will start in Year 7 of the mine life by doubling the size of the Gunnison SX-EW plant.

Excelsior proposes to use the ISR method to extract copper from oxide mineralisation located 91 m to 243 m beneath the alluvial basin fill within the North Star deposit.

ISR is expected to be responsible for 48.4% of the total copper, with an average ‘sweep efficiency’ of 74%. Production for the 24-year life-of-mine is estimated at 2.17-million pounds.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
The economic analysis for the base case before taxes indicates an internal rate of return (IRR) of 48%, a payback of 4.6 years and a net present value (NPV), at a 7.5% discount rate, of $1.17-million.

The estimated after-tax NPV, at a 7.5% discount rate, is estimated at $807-million and the IRR at 40%, with a payback period `of 6.5 years.

Value
The estimated initial capital cost is $46.9-million.

Duration
First copper production from the wellfield is forecast for 2019.

Latest Developments
The Gunnison copper project remains on schedule for first copper production before the end of the year, Excelsior Mining has confirmed, reporting that the drilling of the production wellfield has been completed.

A total of 41 production wells have been successfully drilled to a depth of nearly 400 m each. The company has said that all wells are open within the copper orebody.

The developer will complete the installation of the necessary infrastructure and instrumentation, including stainless steel pumps in the recovery wells.

Working in parallel to the drilling of the injection and recovery wells, 16 compliance and monitoring wells surrounding the production wellfield have also been completed.

Further, the primary header station, which contains piping connections and the controls needed to monitor and adjust flow rates, has been constructed and is ready for commissioning.

Key Contracts and Suppliers
None stated.

On Budget and on Time?
Not stated.