Gold Fields reports delay in first gold from Chile project

15th September 2023 By: Mariaan Webb - Creamer Media Senior Deputy Editor Online

Gold Fields reports delay in first gold from Chile project

Gold Fields CEO Martin Preece

Diversified gold producer Gold Fields has downgraded its 2023 and 2024 production expectations from its new Salares Norte mine, in Chile, owing to a delay in first gold from the project.

In a project update on Friday, the JSE- and NYSE-listed mining firm explained that certain components required commissioning by the original equipment manufacturer (OEM) vendor to maintain the validity of their warranties.

“Challenges in securing the OEM vendor representatives, due to previously announced delays by the main contractor, have resulted in an approximate two-month delay to commissioning of the mills and filter presses,” Gold Fields said.

If first gold is produced on December 1, production for 2023 would be 1 000 gold-equivalent ounces (GEOs), compared with the previously forecast 15 000 to 20 000 GEOs.

Gold Fields cautioned that the production outlook for next year had also been impacted and would fall in the range of 400 000 to 430 000 GEOs, from the previously forecast 500 000 GEOs.

However, should the delay be longer and first gold is only produced by the end of December, 2024’s output will be only 350 000 GEOs at an all-in cost (AIC) of $1 050/GEO.

Despite the downgrade in production for 2023 and 2024, steady state would be reached by the beginning of 2025. Production volumes for 2025 and 2026 remained unchanged at 600 000 GEOs.

Average output for the first six years of the mine life (2024 to 2029) would be 500 000 GEOs, and over the total mine life (2024 to 2033), it averages at 355 000 GEOs.

The project's AIC would average at $700/GEO for the first six years and $780/oz for the total mine life.

Gold Fields, led by CEO Martin Preece, stressed that the Salares Norte remained a world-class project with a payback of less than three years at spot prices.

The company has upped the capital estimate by $20-million to $1.04-billion, owing to the capitalisation of costs following the later start date for first gold.