In the lead-up to achieving its production target of 600 000 t/y, diversified miner Vedanta’s Northern Cape-based Gamsberg zinc mine is ready to launch Phase 1.

D

eveloped over three years by Vedanta’s Zinc International division, the $400-million Gamsberg development forms part of Vedanta’s long-term commitment to the development of the Northern Cape.

In Phase 1, four-million tonnes of ore a year will be produced from Gamsberg’s openpit and 250 000 t/y of zinc in metal concentrate from its concentrator plant.

Phase 2 will see a further investment of between $350-million and $400-million to increase ore mined to eight- million tonnes a year and production of zinc-in-concentrate to 450 000 t/y.

Phase 3, which is expected to start in 2025, will see this increase to 600 000 t/y.

Thus far, 72-million tons of overburden has been prestripped.

Gamsberg, which has the potential to trigger a new wave of industrial and economic development in the Northern Cape, has employed more than 3 000 people during construction over the last two years.

About

750 people are already employed for the operational phase. .