Butcherbird manganese project, Australia – update

28th May 2021 By: Sheila Barradas - Creamer Media Research Coordinator & Senior Deputy Editor

Butcherbird manganese project, Australia – update

Name of the Project
Butcherbird manganese project.

Location
The project comprises eight known manganese mineral resources in an estimated 600 km2 of the southern Pilbara region, in Western Australia.

Project Owner/s
Manganese developer Element 25 (E25).

Project Description
The project has proven and probable ore reserves of 50.55-million tonnes at 10.3% manganese containing 5.22-million tonnes manganese (4.28-million tonnes recoverable manganese).

The May 2020 prefeasibility study (PFS) presented a compelling base case and expansion case economics. The base case assumes the production and sale of 312 000 t/y of medium-grade lump manganese concentrate grading 30% to 35% manganese.

The proposed 1.3-million-ton-a-year processing facility includes crushing, screening, scrubbing, sizing and ore sorting.

The project has a 42-year mine life.

The PFS also highlighted that the project has the potential for significant growth beyond the initial Stage 1 production volumes. The studies examined the potential for an expansion to Stage 1 within 12 months of initial commissioning. The company expects to expedite the expansion of the project once Stage 1 is fully operational.

Potential Job Creation
Not stated.

Net Present Value/Internal Rate of Return
In the base case, the project has an estimated pretax net present value, at an 8% discount rate, of A$441-million and an internal rate of return of 255%, with a payback of six months from the start of operations.

Capital Expenditure
The project has a low capital requirement of $14.5-million, plus $9.2-million in working capital.

Planned Start/End Date
The project construction and start of commissioning were completed within 11 months from the delivery of the prefeasibility published in May 2020.

Latest Developments
E25 has signed a port access agreement with the Pilbara Port Authority, providing use of the Port Hedland Utah Point facility for the bulk export of manganese from the Butcherbird project.

While the terms of the agreement are confidential, E25 has said it is in line with the Pilbara Port Authority’s normal operating terms and satisfies the company’s capacity requirements for the first stage of operations up to 390 000 t/y.

Key Contracts, Suppliers and Consultants
None stated.

Contact Details for Project Information
Element 25, tel +61 8 6315 1400 or email admin@e25.com.au.