600 MW KiPower coal project given environmental go-ahead

6th November 2015 By: Natalie Greve - Creamer Media Contributing Editor Online

The Department of Environmental Affairs (DEA) has granted integrated environmental authorisation (IEA) for the construction of the 600 MW KiPower coal-fired independent power plant, near Delmas, Mpumalanga.

The authorisation comes after the DEA initially rejected the final environmental-impact assessment report for Kuyasa Mining subsidiary KiPower’s proposed plant, citing the need for additional information on the cumulative impacts of the proposed power line connection and the effect on State-owned power utility Eskom’s mooted agreement with regard to the proposed connection options of the independent power producer.

The $1.7-billion facility is planned for development within 5 km of the existing Delmas coal mine, from which it would source coal. It could potentially be expanded to produce up to 2 000 MW in the longer term.

The project will include the development of four 150 MW circulating fluidised bed units, each boasting a 400 kV three-phase transformer, as well as an ash disposal facility.

An 812-m-long sorbent conveyer will transport sorbent from the railyard to the overland coal conveyers, which would carry the coal from the Delmas mine to the new power plant.

The existing railway siding will also be upgraded to provide additional railway siding for limestone delivery and offloading, while several on-site and connecting roads will be upgraded.

Also approved under the IEA are the construction of office areas, a water pretreatment plant, a wastewater treat- ment plant, a sewage treatment works and the establishment of two diesel fuel oil storage tanks.

KiPower expects construction on the power plant to begin this year, with the first of the plant’s three units to be operational by 2018.