$1bn earmarked for AngloGold’s deep-but-cheap Mponeng mine

21st February 2017 By: Martin Creamer - Creamer Media Editor

$1bn earmarked for AngloGold’s deep-but-cheap Mponeng mine

AngloGold Ashanti executive VP Graham Ehm
Photo by: Duane Daws

JOHANNESBURG (miningweekly.com) – A big capital investment is on the cards for AngloGold Ashanti’s Mponeng gold mine, the world’s deepest underground operation.

The former Western Deep Levels Number One operation was on the receiving end of a surfeit of comment when AngloGold Ashanti presented cash-rich results on Tuesday. 

A brownfields expansion feasibility study is expected to be concluded towards the middle of next year on Mponeng, which upped production by 16% and cut all-in sustaining costs by 14% in the 12 months to December 31.

Situated on the Far West Rand, the mine has a large 50-million-ounce resource base and a 12.5-million-ounce reserve at a high grade of 10 g/t.

Up to now, AngloGold Ashanti chief operating officer South Africa Chris Sheppard and his team have been working on a phased development strategy, but that has been swapped for a combined, twin-reef extraction approach, which is looking at shafts and a combination of declines.

The new approach, which optimises the project as a whole, is expected to set up Mponeng as a producer of 450 000 oz/y of gold for more than 20 years, with all-in sustaining costs improving to about $750/oz.

The capital cost of the Mponeng project will be about $1-billion nominal but is spread over ten years with a maximum capital spend of only $80-million a year.

Typical of these deep-level extensions, project execution occurs in parallel with ongoing production over a fairly lengthy period, AngloGold Ashanti executive VP Graham Ehm explained to investors, analysts and journalists at the results presentation, which saw the JSE- and NYSE-listed gold mining company nearly double free cash flow to $278-million on lower production in the 12 months to December 31.

The gold production across AngloGold's 17-mine portfolio in the period was 3.6-million ounces, at a total cash cost of $744/oz.

At Mponeng, work is now progressing to feasibility stage, for completion in the second half of 2018.

Near Carletonville, in the North West, Mponeng is one of the lowest-cost producers in South Africa despite being 3 800 m deep.

   Sheppard commented to Mining Weekly Online earlier this year that Mponeng had shown pleasing improvements, owing to a well-constructed derisked production plan supported by a comprehensive logistics debottlenecking programme, both supported by a disciplined set of management and supervisory work routines.

AngloGold Ashanti CEO Srinivasan ‘Venkat’ Venkatakrishnan made it clear that inward investment in brownfields projects is being prioritised over merger and acquisition possibilities and he identified Mponeng to Mining Weekly Online as an opportunity that offers the best brownfields potential in the South Africa context.

The mine, which has exclusively exploited the Ventersdorp Contact Reef (VCR) orebody down to its current great depth, is to further exploit the VCR but also in future mine the Carbon Leader Reef.

These reefs are mined by the adjacent AngloGold-owned Savuka and TauTona gold mines, which are earmarked for integration into Mponeng in the next 12 to 24 months.

Venkat spoke of targeting after-tax returns in the mid-teens-plus from the company’s brownfields projects, with targets varying from 15% up to 30%.

“I know there’s a case for brownfields projects to go lower but in terms of returns, we’re very focused on it being in the mid-teens-plus,” he said.