https://www.miningweekly.com

Updated study improves Sal da Vida financial returns – Galaxy

22nd August 2016

By: Megan van Wyngaardt

Creamer Media Contributing Editor Online

  

Font size: - +

JOHANNESBURG (miningweekly.com) – Australian lithium miner Galaxy Resources has increased the capital expenditure (capex) estimate of its Sal de Vida project, but has significantly reduced the capital cost payback period and now expects “much more attractive” financial returns from the project in Argentina’s Puna region.

The company on Monday published the results of a revised definitive feasibility study (DFS) for Sal de Vida, which increased capex to $375.5-million, compared with a 2013 study estimate of $369-million. However, the revised DFS has reduced the payback period from four years and seven months in the original DFS to two years and ten months, while improving the net present value to $1.42-billion at an 8% discount rate, compared with $565-million in 2013.

The project is estimated to have the potential to generate average revenues of $354-million a year and average operating cash flow of $273-million a year.

The study is based on resources of 1.1-million tonnes of recoverable lithium carbonate equivalent, as well as 4.2-million tonnes of potassium chloride, supporting production of 25 000 t/y of battery-grade lithium carbonate and 95 000 t/y of potash over a period of 40 years.

Revised DFS operating costs are estimated to be $3 369/t before potash credits and $2 959/t after a potash credit of $410/t for each tonne of lithium carbonate produced. This is 17% higher than its previous estimation in 2013.

The DFS has been modelled on an operation with production at these levels, assuming an initial three-year ramp-up for lithium carbonate production to achieve full capacity, with potash production assumed to be deferred by one year for production start with a two-year ramp-up to achieve its planned production capacity.

Galaxy acquired the Sal de Vida project in July 2012 from the merger with Lithium One, and at that time only a preliminary economic assessment had been completed.

The company has since funded the completion of the original DFS, which included extensive hydrology work and modelling, drilling, pump tests, resource development, pilot plant testwork, flow sheet development and engineering, logistics, market and financial modelling.

Edited by Mariaan Webb
Creamer Media Senior Deputy Editor Online

Comments

The content you are trying to access is only available to subscribers.

If you are already a subscriber, you can Login Here.

If you are not a subscriber, you can subscribe now, by selecting one of the below options.

For more information or assistance, please contact us at subscriptions@creamermedia.co.za.

Option 1 (equivalent of R125 a month):

Receive a weekly copy of Creamer Media's Engineering News & Mining Weekly magazine
(print copy for those in South Africa and e-magazine for those outside of South Africa)
Receive daily email newsletters
Access to full search results
Access archive of magazine back copies
Access to Projects in Progress
Access to ONE Research Report of your choice in PDF format

Option 2 (equivalent of R375 a month):

All benefits from Option 1
PLUS
Access to Creamer Media's Research Channel Africa for ALL Research Reports, in PDF format, on various industrial and mining sectors including Electricity; Water; Energy Transition; Hydrogen; Roads, Rail and Ports; Coal; Gold; Platinum; Battery Metals; etc.

Already a subscriber?

Forgotten your password?

MAGAZINE & ONLINE

SUBSCRIBE

RESEARCH CHANNEL AFRICA

SUBSCRIBE

CORPORATE PACKAGES

CLICK FOR A QUOTATION